試卷名稱
考試中心《》在線考試
試卷年份2010年下半年
試題題型【單選題】
試題內(nèi)容

Project schedule management is made up of six management processes including:activity definition, activity sequencing,(  ) , and schedule control by order.
A.a(chǎn)ctivity duration estimating, schedule developing, activity resource estimating
B .a(chǎn)ctivity resource estimating, activity duration estimating, schedule development
C.schedule developing, activity resource estimating, activity duration estimating
D.a(chǎn)ctivity resource estimating, schedule developing, activity duration estimating

查看答案